MPE Milestones and Goals

  • Spring 2024 MPE Predevelopment work commenced

  • Oct 2024 WAPA application accepted

  • Jan 2025 MPE pre application submitted to Shasta County

  • June 2025 WAPA Feasibility Study completed

  • August 2025 WAPA System Impact study commenced

  • Sept 2025 MPE Use permit submitted to Shasta County